Prestige Parklane Project Schedule

Prestige Parklane Project Schedule | Milestones


The Prestige Parklane project schedule runs from building plan approval on 13 August 2026 to a declared completion on 31 December 2030. Construction starts on 1 October 2026. The payment schedule runs alongside it on fixed calendar dates. The first instalment is due on 10 December 2026.

Prestige Parklane Project Timeline


Here is the full Prestige Parklane project timeline, from land approval to possession:

Date Milestone
16 July 2025 E-Khata issued for the Phase 1 land
13 August 2026 Building plan approved by KIADB, DO3-KIADB-00128/26-27/BP
21 August 2026 RERA application acknowledged
15 September 2026 Karnataka RERA registration granted, and the EOI opened
25 September 2026 Project launch, with tower-wise price sheets released
1 October 2026 Construction start, as declared to RERA
10 December 2026 First time-linked instalment falls due
10 October 2030 Last of the 24 instalments
31 December 2030 Proposed completion filed with RERA
6 January 2031 Possession

Prestige Parklane Approvals Before Launch


Prestige Parklane approvals were in place before the launch. KIADB approved the building plan on 13 August 2026. Karnataka RERA granted registration on 15 September. Both came before any price was published.

Buyers at launch had the land title, the sanctioned plan, the unit count and the completion date on public record before paying. The project was not sold on a plan still waiting for approval.

Prestige Parklane Construction Period


The Prestige Parklane construction period is just over four years. Work begins on 1 October 2026 and runs to a declared completion on 31 December 2030. The early months go into the ground, because each of the nine towers has three basement levels.

Above ground, the towers rise to 76.55 m, with a ground floor and 24 upper floors. The 19th floor of each tower is a refuge floor. Larsen & Toubro is the contractor for the build.

Prestige Parklane Payment Schedule


The Prestige Parklane payment schedule is time-linked, not construction-linked. Instalments fall on fixed dates, whatever the stage on site.

Stage Payment When
Booking 10% + GST On booking
Agreement 10% + GST On signing the agreement for sale
Instalments 1 to 24 3.2% + GST each Every two months, 10 December 2026 to 10 October 2030
Possession 3.2% + GST On intimation of possession, 6 January 2031
Other charges 100% + GST On intimation of possession

Plan your cash flow around these dates, not around site progress. The two are kept separate in this project.

Quarterly RERA Progress Updates


Quarterly RERA progress updates start once construction begins. The promoter must file each update with Karnataka RERA within 15 days of the end of the quarter. The project engineer certifies progress in Form 3 and the architect in Form 2. These filings are the most reliable public record of the build.

Buyers can check progress four times a year. You do not need to rely on a sales update or a site photo shared on a group chat.

Prestige Parklane Current Status


The Prestige Parklane current status is site preparation. The land at Plot No. 24 is demarcated and fenced. The KIADB approach and arterial roads are complete, with carriageway, lighting and a planted median. Site services are being installed. The experience centre and model flat are under construction. Tower work begins on 1 October 2026.

Which Project Dates Are Legally Binding?


Two Prestige Parklane project dates are legally binding. These are the construction start of 1 October 2026 and the completion of 31 December 2030, both declared to Karnataka RERA. If possession runs past the completion date, the Act requires the developer to pay buyers interest for every month of delay.

The rest of the schedule helps with your own planning. It runs from the first instalment in December 2026 to the possession charges due at the end.

FAQs


1. When does construction start at Prestige Parklane?

On 1 October 2026, the start date declared to Karnataka RERA, giving a build of just over four years.

2. What is the project completion date?

31 December 2030, filed with Karnataka RERA as the proposed completion date. Possession follows on 6 January 2031.

3. When is the first payment instalment due?

The first time-linked instalment falls on 10 December 2026, and the last on 10 October 2030.

4. Is the payment plan linked to construction stages?

No, it runs on fixed calendar dates, so instalments fall due whatever stage the site has reached.

5. How often is progress reported?

Every quarter, within 15 days of the quarter ending, with the engineer and architect certifying progress in RERA Forms 3 and 2.

6. Were approvals in place before the launch?

Yes. KIADB approved the plan on 13 August 2026 and RERA registration followed on 15 September, ahead of the 25 September launch.