Prestige Parklane Construction Update 2027

Prestige Parklane Construction Update 2027 | Quarterly Progress


Prestige Parklane construction update 2027 tracks site activity across all 9 towers in KIADB Phase 2 by quarter. The launch was 25 September 2026. Possession is set for 6 January 2031, about 51 months from launch. This is a standard timeline for a G+24 project of this scale. Each update on this page uses confirmed data only, from the builder's official communication or the RERA quarterly filing. Estimates and projections are not shown as fact. Buyers can cross-check every figure on the Karnataka RERA portal using the project registration number.

Prestige Parklane RERA Construction Schedule


The Prestige Parklane RERA construction schedule was submitted with the Karnataka RERA registration. Each activity has a builder-committed start and end date. These are legal commitments, not estimates. Any change must be reported to RERA and is visible on the public portal under registration number PRM/KA/RERA/1251/309/PR/150926/008941.

Sub-Structure

Activity Start Date End Date
Earth work and site leveling 1 Oct 2026 31 May 2027
Foundation footing work 1 Mar 2027 30 Sep 2027
Up to Plinth Level 1 Mar 2027 31 Jan 2028
Sub-structure flooring — basement and parking 1 May 2027 31 Jan 2028
Retaining wall (all types) 1 Jun 2027 31 Dec 2027

Super-Structure

Activity Start Date End Date
RCC framed structure 1 Feb 2028 31 Oct 2029
Masonry construction 1 Apr 2028 28 Feb 2030
Plastering — inside, outside and ceiling 1 Aug 2028 30 Jun 2030
Joinery — doors, windows and ventilators 1 Oct 2028 31 Aug 2030
Water supply, sanitary and electrification (basic) 1 Nov 2028 30 Sep 2030
Flooring, tiles, dadoing and skirting 1 Dec 2028 31 Oct 2030
Railing and grill fixing 1 Jan 2029 30 Nov 2030

Finishing Works

Activity Start Date End Date
Electrification, water supply and sanitary finishing 1 Dec 2028 30 Sep 2030
Painting 1 Apr 2029 31 Dec 2030
Fire prevention and firefighting systems 1 Mar 2029 30 Sep 2030
Weather-proof work — tiles and concrete 1 Feb 2029 30 Jun 2030
Elevation work 1 May 2029 31 Jul 2030
Internal and external landscaping 1 Mar 2029 31 Dec 2030

All finishing activities close by December 2030. The committed possession date follows on 6 January 2031. Wardrobe, kitchen cabinet and puja work are listed as not applicable in the RERA filing. They are not part of the builder's scope for this project.

Prestige Parklane Q4 2026 Update (October–December 2026)


The Prestige Parklane Q4 2026 update covers site activity from October to December 2026. The update date is November 2026. The project is at the site preparation stage. This is normal for the first quarter after launch.

Earth work and site levelling is the first activity in the RERA construction schedule, with a declared start of 1 October 2026. The 11.91-acre residential land is demarcated and fenced. The KIADB approach roads are complete, and the experience centre is being built. Work on the nine towers has not yet reached piling or foundations. The enterprise estate is a planned future phase and is not part of the current construction.

Tower / Block Stage — Q4 2026 Notes
Tower 1 Site preparation Tower work not yet started
Tower 2 Site preparation Tower work not yet started
Tower 3 Site preparation Tower work not yet started
Tower 4 Site preparation Tower work not yet started
Tower 5 Site preparation Tower work not yet started
Tower 6 Site preparation Tower work not yet started
Tower 7 Site preparation Tower work not yet started
Tower 8 Site preparation Tower work not yet started
Tower 9 Site preparation Tower work not yet started
Enterprise Estate Planned future phase Planned data centres, factory block, warehouse

The project is on schedule as of this update. The possession date of 6 January 2031 stands. A G+24 tower with 3 basements needs about 51 months from launch to possession. The current pace is in line with that target.

Q1 2027 Update (January–March 2027)


This section will be updated in April 2027 with confirmed progress from the builder and the RERA quarterly filing.

Q2 2027 Update (April–June 2027)


This section will be updated in July 2027 with confirmed progress from the builder and the RERA quarterly filing.

Q3 2027 Update (July–September 2027)


This section will be updated in October 2027 with confirmed progress from the builder and the RERA quarterly filing.

Prestige Parklane Construction Update Sources


Prestige Parklane construction updates on this page are refreshed each quarter. Every update uses confirmed information only. The source is either the builder's official communication or the RERA quarterly filing. No estimates or projections are shown as fact.

Each update restates the committed possession date. That date is 6 January 2031. Progress photos on this page come from the actual site. Renders are not used in place of site photos.

Buyers can track progress independently. The RERA portal lists all filings under registration number PRM/KA/RERA/1251/309/PR/150926/008941. The portal is managed by the Karnataka government. It shows quarterly construction updates filed by the builder. This is the most reliable independent source for buyers.

The project spans 9 towers. Each tower is G+24 floors with 3 basements. The total height is 76.55 m. There are 1,788 apartments across 37 layouts. Sizes range from 567 to 1,801 sq ft. The enterprise estate on the same site is planned as a future phase with data centres, a factory block and a warehouse. This makes it a large mixed-use project.

Prestige Group has delivered projects in this area before. Prestige Golfshire and Prestige Park Drive are both in Devanahalli. The group was founded in 1986. It is listed on the NSE and BSE. It has completed over 300 projects and more than 200 million sq ft across India. This track record helps when judging whether the project will be delivered on time.

Prestige Parklane Enterprise Estate: Upcoming Phase


The Prestige Parklane enterprise estate covers 20.35 acres of the total 32.26-acre site. It is on the same campus as the nine apartment towers. It is planned as the upcoming Prestige Technology and Logistics Hub, with three data centres, a warehouse, a factory block and a 220 KV substation. It is a future phase. Only the residential Phase 1, with nine towers and 1,788 homes, is RERA-registered and under way. The estate sets the project apart. No competing KIADB Phase 2 project plans data centres and a factory block with apartment homes on one campus. For buyers, the estate is planned to add an employment base within walking distance of the towers once it is built.

Next Prestige Parklane Construction Updates


The next Prestige Parklane construction updates will add confirmed data to the relevant sections above. Q1 2027 data will appear in April 2027. Q2 2027 data will appear in July 2027. The committed possession date is restated in every update. If that date changes for any reason, it will be shown clearly. The Karnataka RERA portal reflects any date change as soon as the builder files it. That filing is public. Buyers should check both this page and the RERA portal to stay current.

Frequently Asked Questions


1. What is the current construction status of Prestige Parklane?

As of November 2026, the project is at site preparation. All nine towers are yet to start piling. The enterprise estate is a planned future phase.

2. What is the committed possession date?

The committed possession date is 6 January 2031. RERA registers the completion date of 31 December 2030. Neither date has changed as of this update.

3. How can buyers track construction independently?

Buyers can visit the Karnataka RERA portal. Search for registration number PRM/KA/RERA/1251/309/PR/150926/008941. Quarterly filings from the builder appear there.

4. How often is this page updated?

This page is updated once every quarter. Each update reflects confirmed data from the builder or the RERA quarterly filing. No estimates are published as confirmed progress.

5. How many towers and floors does Prestige Parklane have?

The project has 9 towers. Each tower is G+24 floors with 3 basements. The total height per tower is 76.55 m.

6. What happens if the project is delayed?

RERA requires the builder to notify buyers of any change to the possession date. Buyers are entitled to compensation under the RERA Act for delays. The Karnataka RERA portal will reflect any revised timeline if one is filed.